PTC BMX track TO DO
list Date: July 2006
Item# |
Priority |
Task
Description |
Contact |
Due
date or Dependency |
01 |
|
Fix
drainage and erosion issues, (sod, straw mat, sandbags, earthmoving) |
Ant,
team |
ongoing |
02 |
|
Fence
perimeter (black chainlink approved) 4ft, count
runs, gates |
Steve
Z |
|
03 |
|
Prepare,
Asphalt/polypave
last turn |
City,
team |
|
04 |
|
Fix
gate – reweld mesh, sheet-metal, use metal plates
for ID, or wood |
Brian
N /Candy |
|
05 |
|
Build
corner marshal platforms, add umbrella holes (home depot) |
Steve
Z |
|
06 |
|
|
|
|
07 |
|
Repair
C/H air compressor – install new pressure switch |
Don |
|
08 |
|
Relocate
compressor to toolroom |
Don |
|
09 |
|
|
|
|
10 |
|
Fix/rebuild
toolroom door (doorjam
support) |
Brian
D |
|
11 |
|
Solve
start lights cable routing (carpet, pvc) from |
Brian
D |
|
12 |
|
Organize
connectors for |
|
|
13 |
|
Build
moisture-proof box for PA system, quick-connect, Power-strip
|
Don |
|
14 |
|
Repair
floodlight |
City |
|
15 |
|
Restore
power to toolroom, install bulb, build guard around
bulb |
City/Ant |
|
16 |
|
Ensure
2 faucets working (pressure and flow), hatches above grade |
City/Ant |
|
17 |
|
Cut
large door in back of toolroom – allow 4-wheeler to
be stored at track |
Anthony |
|
18 |
|
Service
oil air Ram and piston, lower pressure to where can still raise gate |
Anthony |
|
19 |
|
Install
motion detector light between 2 buildings (CrimeSafe) |
Brian D |
|
20 |
|
Ask
Bobbie (CrimeSafe) to add speaker/s to PA for
concessions |
Anthony |
|
21 |
|
Get
CD player with radio (digital tuner) – test reception before buying |
Brian
D |
|
22 |
|
Complete
paving access paths behind staging, concessions, road access |
|
|
23 |
|
Retrieve
keys from Steve, reissue to Don |
Anthony |
|
24 |
|
Need
steel grates (3) to cover drain entrances on track (safety issue) |
City |
|